CV Step Setup

Latest updated: Mar 28, 2025
Video recording version: 8.0.0.490, compatible with BTS 8.0 software.

How to Set Up Steps for Cyclic Voltammetry (CV)

  • 1. Right-click the battery's corresponding channel, select "Single Start" to access the step configuration interface.

  • 2. Choose the cyclic voltammetry step and double-click the box for step time or voltage to enter the CV step settings.

  • 3. In the dropdown menu: "OCV" represents Open Circuit Voltage, while "Ref" stands for Reference.

  • 4. Example settings: initial voltage at 0 V vs. OCV, scan rate at 1 mV/s, vertex voltage 1 at 3.9 V vs. Ref, vertex voltage 2 at 2.6 V vs. Ref, 5 cycles, and voltage record at 3 mV.

  • 5. Select a current range exceeding the maximum scan current. Set the final voltage to 0 V vs. OCV (uncheck the box to disable if needed).

  • 6. After setup, click OK, then Start in the lower-right corner to begin testing.

  • 7. Post-test, open the data, click the CV icon to view the graph. Check the cycle count box, use the right-side buttons or input the cycle number to see each cycle's graph.

  • 8. Right-click the graph area to copy data of the displayed graph.

This operation video tutorial is applicable to the following products:
● CT/CTE-8000 Battery Testing System Series (CT-8002Q-5V100mA)

neware-battery-test-car-battery-test



· Related Article

NEWARE and Cookies
We use Cookie to personalize and improve your experience with our website. By continuing to browse the site you are agreeing to our use of cookies.