Single start and All tart

Latest updated: Dec 15, 2023
Video recording version: 8.0.0.483, compatible with BTS 8.0 software.

Today,we will demonstrate the differences between Single start and All start, as well as how to perform All start.


  • Open the BTS software, right-click on the test channel. You will see the first option as "Single start", which allows you to start testing on a single channel. 

  • Click on "Set" at the top, then click on "System settings", followed by "Display settings". 

  • In the Right-click menu function, locate "All start" and check the box.

  • Save the changes and enter the password "neware". 

  • Go back to the channel interface and right-click on the test channel to find the "All start" option. All start is mainly used for large-scale testing in enterprise production.


That wraps up the entire demonstration. Thanks for watching.

This operation video tutorial is applicable to the following products:
● CT-4000 Battery Testing System Series (CT-4008Q-5V100mA, CT-4008Q-5V6A-S1, CT-4008Q-5V6A-164, CT-4008Q-5V12A-S1, CT-4008Q-5V12A-164, etc.)
● CE-6000 Battery Testing System Series (Cell, Module, Pack, etc.)
● CT/CTE-8000 Battery Testing System Series (CT-8002Q-5V100mA, CTE-8008-5V200A, etc.)
● All-in-One Battery Testing System Series (WHW-25L-S-16CH, WIHW-200-160CH-B, WHW-100L-2-160CH, WHW-500L-5V6A80CH-380V, WGDW-380L-2-40BFC-5V600A8CH, etc.)



· Battery Exhibitions